We have completed the Ground Floor slab pour, plumbing drains & brick load
Ground Floor brickwork is progressing
Prior to Christmas we have scheduled the First Floor slab to be formed up, reo install, electrical & plumbing prelays & the suspended slab pour for curing over the Christmas break
Banool Crescent City Beach
November Update
First Floor cladding, texture & glazing has been completed
First Floor cabinets install & tiling has started
The basketball court has been fully scaffolded & wiring, aircon & plumbing has been completed & we are starting the ceiling framing next week