Coming Soon… New Display Home City Beach

February 2024

  • We have our First Floor Slab loaded with bricks & our structural steel is installed
  • We have our First Floor scaffold lifted, T-Bars are installed & brickwork is now 95% completed

January 2024

  • We have had a huge progressive work month again! Achieving our January goals, we have poured the FF slab & let it cure over the Christmas Break
  • Stripped & removed formwork, installed scaffold, GF & FF structural steel & columns installed & completed brick loading the FF slab

December 2023

  • We have made massive progress this month including loading the ground floor slab, completed ground floor brickwork & installed all structural steel
  • Reaching our December goals, we have completed the first floor formwork, installed handrails, installed all structural steel & had the reo installed & inspected
  • All electrical, plumbing & air con prelays have been completed & we will pour the concrete suspended slab on the 22/12 to cure over the Christmas Break.

November 2023

  • We have completed the Ground Floor slab pour, plumbing drains & brick load
  • Brick walls are progressing for Ground Floor
  • Before Christmas we have scheduled the First Floor slab form, reo install, electrical & plumbing prelays & pour the suspended concrete slab for curing over the Christmas break. 
  •  

October 2023

  • We have completed the new boundary wall & poured the new pool shell
  • Earthworks is now completed & GF footings / slab has commenced

September 2023

  • We have completed a stunning, modern & boutique home design & have submitted to the shire for Building Permit
  • Working & Structural drawings have been completed & scheduling is underway
  • Site preparation has commenced & so has replacing the collapsed boundary wall 
  • We are scheduled to pour the shell of the pool early October once we have received the Building Permit

August 2023

  • We have completed a stunning, modern & very boutique home design & have now received the DA Approval
  • The demolition of the old home is now complete
  • Selections, Working & Structural Drawings are progressing & all going to plan, we will start quoting in September
  • We are working towards breaking ground early October
  •  

July 2023

  • We have completed a stunning, modern and very boutique home design and submitted the drawings to shire for DA approval
  • Selections, Working & Structural Drawings have commenced & we are waiting on DA approval to complete these & start quoting
  • The tired old 1960’s home has been demolished & we are working towards breaking ground in September / October

June 2023

  • We have completed a stunning, modern and very boutique home design and submitted the drawings to shire for DA approval
  • Selections, Working & Structural Drawings have commenced & we are working towards breaking ground in September after we demolish the existing tired old home

May 2023

  • We have completed a stunning, modern and very boutique home design and submitted the drawings to shire for DA approval
  • Selections, Working & Structural Drawings have commenced & we are working towards breaking ground in September after we demolish the existing tired old home

April 2023

  • We have completed a stunning, modern and very boutique home design and submitted the drawings to shire for DA approval
  • Selections, Working & Structural Drawings have commenced & we are working towards breaking ground in September after we demolish the existing tired old home

COMMENT

ENQUIRE NOW

Experienced, Professional, Transparent

As a highly awarded and recognised luxury home builder in Perth, we are here to work with people who are at a certain stage in their lives, either financially, or in terms of the lifestyle they want to live.

ONLINE ENQUIRY
  • This field is for validation purposes and should be left unchanged.

City Beach

February Update

  • First Floor Slab is loaded with bricks and structural steel has been installed
  • First Floor scaffold has been lifted, TBars have been installed & brickwork is now 95% complete

Banool Crescent City Beach

February Update

  • Front Elevation is looking great now the scaffold has been removed
  • The office & ensuite cabinets & stone has been installed
  • The Basketball Court concrete floor has now been poured