Victoria Avenue Project in Claremont Monthly Updates

January

Over the last month, the Victoria Avenue project in Claremont has come a long way, with it continuing to take shape nicely.

The bricklayers have been progressing well with boundary walls and retaining walls going up. The bathrooms have had the tilers painstakingly laying superb, high-quality Australian made tiles, and they have also moved onto tiling the ample balconies too.

Jason windows continue to be installed throughout the premises by the glaziers, and the plasters are busy putting up gyprock on internal walls.

Heading outside to the magnificent pool area, and a beautiful acrylic texture has started to be applied.

February

Since we have recommenced work in January, Outstanding progress has been achieved and many milestones accomplished . Among these we have completed all the aluminium glazing, so the home is now fully locked up on all levels .The kitchen and all cabinetry has been installed and the stone benchtops are in the process of being manufactured. The Internal and external tiling is progressing well, and the aluminium feature external aluminium cladding has started being laid on the external textured walls.

We are now only 5 months away from completion. Right now, is an ideal time to arrange a personal visit to the home and see for yourself the quality and level of detail we take pride in providing to our valued Clients.

As this home has now progressed substantially, it’s definitely beginning to turn heads from locals and passing motorists.

March

Over the past month we have been working proactively with many contractors on the finishing of this magnificent home. Most of the cabinetry supplied by International cabinets have been installed as have the porcelain benchtops by Demelio stone. Our tiler, Joel, is doing exceptional work on the detailed tiling and paving – The feature stone clad walls on the Front elevation ,entry and pool are a real eye catcher. Our painters are preparing the walls and doors and we are in the process of fitting out the electrical and plumbing.

We are on target with our completion timeline for August and look forward to the work fitting off the materials over the next few months that will take this home to the exceptional standard we demand.

Right now is an ideal time to arrange a personal visit to the home and see for yourself the quality and level of detail we take pride in providing to our valued Clients.

April

Since our March update we have made extensive progress with all works on site .

The Victoria Avenue elevation of this home is really starting to take shape now , with the breezeway frame now installed as a bridge across the driveway, when this is clad with Aluca bond it will make a grand entrance to this stately home .

We have poured the concrete to the driveway and this will be the base to the tiled drive.

Our tilers have been busy laying the alfresco stone and extensive large format floor tiles throughout which look amazing . The electrical and plumbing fit offs are evolving, the custom cool room has been built and painting is underway .

The three-level glass and stainless steel lift which will service all floors is now installed and will be a highlight when it is lit up and finished .

We are on target with our completion timeline for August and look forward to continuing the detailed work fitting off the finishing materials over the next few months that will take this home to the exceptional standard we demand .

May

We have been very busy working on Victoria Avenue in May and we are spot on target to complete in August. We are looking forward to continuing the detailed work fitting off the finishing materials over the next few months that will take this home to the exceptional standard we demand

Externally, the exposed aggregate has been poured and the tiling and stone cladding has progressed. Indoors, the cabinetry fit off is nearly complete, looking sleek and stylish. The timber flooring and treads are being installed and the electrical and plumbing fit off is well underway. Right now all the necessities of a bespoke home are going into this home, outstanding feature fittings and everything one would need to create their ultimate luxury home. Topping off this home’s quality inclusions, has to be the 3-level stainless steel and glass elevator which has been installed and is looking sharp.

Right now, is an ideal time to arrange a personal visit to the home and see for yourself the quality and level of detail we take pride in providing to our valued Clients. 

June

We have been steadily making progress throughout June and are on target to complete in early August and look forward to continuing the detailed work, fitting off the finishing materials over the next few months that will take this home to the exceptional standard we demand .

The riverside elevation has been a focus in June and is nearing completion. The stone and aluminum cladding has been completed and the undercroft is making great progress towards completion. Inside, a bathroom feature, tiled wall, has been set up and is looking inspiring. The ensuite is also beginning to take form. The Victoria Avenue entrance bridgeway is underway and taking shape beautifully, adding to the many unique features of this home.

Right now, is an ideal time to arrange a personal visit to the home and see for yourself the quality and level of detail we take pride in providing to our valued Clients.

July

Our early August completion target date has been delayed due to three weeks of consistent rain throughout July. This has prevented river access however; we have been working and completing all the internal work as much as we are able to.

All detailed works such as fitting off the finishing materials to this amazing home and completing our clients home to the exceptional high standard we demand, is what we at Exclusive Residence live for. This unique home with its exceptional Swan River views from the stone clad balcony is just breathtaking. This home has four staircases, with access points to the front entry and lift. The basement pond with stone edge detail, laid by Joel and his team looks outstanding, well done to our master craftsman.  Also looking great is the aluminium screening against the stone texture.

The Victoria Avenue entry garage door and stone paving is looking sharp. Large entry pivot doors and aluminium cladding against porcelain and texture are just some of the unique details of this sophisticated home. Inside the brass basin spout sets off the many textures in the ensuite too.

Right now, is an ideal time to arrange a personal visit to the home and see for yourself the quality and level of detail we take pride in providing to our valued Clients. 

August

Our August Completion target date has been pushed back to September due to weeks of consistent winter rain.

The detailed final handover works are well underway, fitting off and cleaning the finishing materials to this amazing home will deliver our clients the exceptional high standard we demand. This month we have put the finishing touches to the carport, the stone, aluminium cladding, timber and tiles showcase how outstanding design and colour can influence a luxury home. Inside the kitchen cabinets and stonework have been completed. Outside the pool and alfresco area is looking truly stylish, architecturally functional combined with designer style.

Check back in next month to view the unveiling of this luxury Perth home.

September

The wait is nearly over! The detailed handover works are now underway. The finishes scream luxury in both the kitchen and bathroom. The Claremont château is available for viewing for personal visits. Come and see what the Exclusive Residence difference is. Imagine yourself in the elegance and high quality that our valued clients know and expect.

October

The lifestyle of this house is really what drew our interest from the beginning. The river provides the perfect backdrop to this astonishing living area. Our final touches have been placed on this property and our Clients will be nearing the finish line too. This Riverside manor will be photographed so you can see the landscaping and pool in all its glory.

November – December

Our final touches have been placed on this property and our Clients will be nearing the finish line too. This Riverside manor will be photographed so you can see the landscaping and pool in all its glory.

January – February

We have handed over this home now and our Client is working to complete the pool and landscaping so we can provide even more amazing photos of this iconic Riverside castle

Right now, is an ideal time to arrange a personal visit to the home and see for yourself the quality and level of detail we take pride in providing to our valued Clients.

Arrange a Site Visit to This Superb Property

This custom luxury home will arguably be Victoria Avenue’s most prestigious property, and we invite potential clients the chance to come on-site and see the construction for themselves.

See and feel the construction process for yourself, the craftsmanship, and the efficient site works, with our Managing Director, John Douglas.

If you are planning on building a custom luxury home in Perth and are looking for a premium custom home builder, then this is the opportunity to get on the ground and see it for yourself.

Simply call our office, or provide your details on the contact form and we’ll promptly be in touch with you to schedule this one on one site visit.

COMMENT

ENQUIRE NOW

Experienced, Professional, Transparent

As a highly awarded and recognised luxury home builder in Perth, we are here to work with people who are at a certain stage in their lives, either financially, or in terms of the lifestyle they want to live.

ONLINE ENQUIRY
  • This field is for validation purposes and should be left unchanged.

City Beach

February Update

  • First Floor Slab is loaded with bricks and structural steel has been installed
  • First Floor scaffold has been lifted, TBars have been installed & brickwork is now 95% complete

Banool Crescent City Beach

February Update

  • Front Elevation is looking great now the scaffold has been removed
  • The office & ensuite cabinets & stone has been installed
  • The Basketball Court concrete floor has now been poured